Title |
On UFR Settings Considering Wind Power Fluctuation In Jeju Island |
Authors |
박민수(Park, Min-Su) ; 전영환(Chun, Yeong-Han) ; 변성현(Byun, Sung-Hyun) ; 양정재(Yang, Jeong-Jae) |
DOI |
https://doi.org/10.5370/KIEE.2014.63.4.445 |
Keywords |
Wind power ; HVDC ; UFR ; Load shedding ; Jeju |
Abstract |
Jeju power system is connected to the mainland power system through HVDC, and receives about half of required electricity through the HVDC lines. Jeju power system already experienced black out when a generator tripped at the moment of the HVDC line faults. But, UFR operated as was expected when HVDC line fault occurred at that time. As the penetration level of wind turbines increases, it is required to set UFR again considering intermittent wind turbin outputs. In this paper, we address a new way of UFR setting through computer simulation. |